Construction Camera

  1. Primrose

    Primrose Project Basement Floor RCC casting, Pile Cap rebar fabrication, UGWR NCF works.

    Md. Monirul Alam

    Mr. Monirul Alam project RCC casting of column, Brick work, Shuttering of roof beam.
  2. Md. Monirul Alam

    Mr. Monirul Alam project 7th floor rebar fabrication, level checking work.
  3. Md. Monirul Alam

    Mr. Monirul Alam project Rebar fabrication of slab, Rebar fabrication of stair, Plastering work.
  4. Md. Monirul Alam

    Mr. Monirul Alam project 5th Floor Shuttering and beam centering, Checking level, Rcc casting and shear wall work.
  5. O2 Center

    O2 Center project curtain wall work.

    Md. Monirul Alam

    Mr. Monirul Alam project block making and shuttering for slab work.
  6. Md. Monirul Alam

    Mr. Monirul Alam project ground floor brick wall, 2nd floor Centering removal, 3rd floor Centering work.
  7. Md. Monirul Alam

    Mr. Monirul Alam project rebar fabrication of beam, Shuttering, Shear wall casting work.

    Universal Jeans Ltd.

    Universal Jeans project successfully completed and handover.

    O2 Center

    O2 Center project rooftop plaster work.
  8. Universal Jeans Ltd.

    Universal Jeans project semi basement brick, lintel casting and stair patch work.

    O2 Center

    O2 Center project rooftop slab rebar placing work.
  9. O2 Center

    O2 Center project lift machine room plaster work and drain shutter work
  10. O2 Center

    O2 Center project brick wall and grill work
  11. Universal Jeans Ltd.

    Universal Jeans project skirting patchwork and kitchen plaster work.
  12. Universal Jeans Ltd.

    Universal Jeans project Front elevation, Decorative slab, Electric duct brick work

    National Hospital

    National Hospital project successfully completed and handover.
  13. Universal Jeans Ltd.

    Universal Jeans project OHWT & liftmachineroom outside plaster work.

    Bakul Monzil

    Bakul Monjil project successfully completed and handover.
  14. Bakul Monzil

    Bakul Monzil project out side plaster and groove work completed.

    Universal Jeans Ltd.

    Universal Jeans project OHWT wall and column tie placement, centering.
  15. Universal Jeans Ltd.

    Universal Jeans project north side external plaster, OHWT bottom slab rebar placement, decorative slab rebar fabrication work.

    Bakul Monzil

    Bakul Monzil project boundary wall grill, lift machine room plaster work.
  16. Universal Jeans Ltd.

    Universal Jeans project lift machine room bottom slab rebar placement and west side external plaster work.

    Bakul Monzil

    Bakul Monzil project east, west out side plaster work.
  17. Bakul Monzil

    Bakul Monzil project void portion plaster work and roof top one room and OHWR second bottom slab rebar placing work.

    Universal Jeans Ltd.

    Universal Jeans project outside plaster, 7th floor inside plaster work.

    Digital Traffic Management (DTM)

    DTM project Police Box Exterior and Interior Work Completed at Kazir Dewri Junction.
  18. Bakul Monzil

    Bakul Monzil project 8th floor brick wall work, 9th floor inside plaster work, Roof top second lift column casting work.

    Universal Jeans Ltd.

    Universal Jeans project 7th floor electric groove work and 9th floor ceiling plaster work.

    Digital Traffic Management (DTM)

    DTM project Police Box Exterior and Interior Work at Kazir Dewri Junction.
  19. Bakul Monzil

    Bakul Monzil project 8th floor brick work and Meter room brick work.

    Universal Jeans Ltd.

    Universal Jeans project 2nd floor brick wall plaster & 7th floor brick masonry and 8th floor ceiling plaster work.

    Digital Traffic Management (DTM)

    DTM project police box 1st floor, 2nd floor exterior work at kazir dewri junction.
  20. Bakul Monzil

    Bakul Monzil project 7th floor lintel, ceiling plaster and false slab shutter work and brick work.

    Universal Jeans Ltd.

    Universal Jeans project 6th floor & 7th floor brick masonry work.

    Digital Traffic Management (DTM)

    DTM project police box 1st floor exterior and interior work at kazir dewri junction.
  21. Bakul Monzil

    Bakul Monzil project 6th floor brick work, 7th floor brick work and OHWR coloum work.

    Universal Jeans Ltd.

    Universal Jeans project 5th floor brick masonry & 6th floor brick masonry and 9th floor beam slab shutter opening work.

    Digital Traffic Management (DTM)

    DTM project Police Box foundation work at Kazir Dewri Junction.
  22. Bakul Monzil

    Bakul Monjil project 5th floor brick work and 6th floor ceiling plaster work.

    Universal Jeans Ltd.

    Universal Jeans project 6th floor ceiling plaster, 7th floor brick work & Top floor slab casting work.

    Digital Traffic Management (DTM)

    DTM project road cutting for footpath beautification at Kazir Dewri Junction.
  23. Universal Jeans Ltd.

    Universal Jeans project 9th floor column & share wall casting work.

    Bakul Monzil

    Bakul Monjil project 3rd floor plaster work, 4th floor brick wall work and 5th floor brick wall layout work.

    Digital Traffic Management (DTM)

    DTM project Layout marking work at Kazir Dewry Junction.
  24. Universal Jeans Ltd.

    Universal Jeans project 7th floor column & share wall casting and beam bottom shutter fitting work.

    National Hospital

    National Hospital project entry side cludding bricks work.
  25. Dr. Salim Ahmed

    Dr. Salim Ahmed project successfully completed and handover.

    Bakul Monzil

    Bakul Monzil project 2nd floor electric groove cutting, grill fitting and toilet door fitting work and 3rd floor brick wall work.

    Universal Jeans Ltd.

    Universal jeans project 1st floor brick layout & 6th floor column shutter fitting work.
  26. Mothers Heaven

    Mothers Heaven project 8th floor roof beam & roof slab rcc casting work completed.

    Dr. Salim Ahmed

    Dr. Salim Ahmed project retrofitting work completed.

    Universal Jeans Ltd.

    Universal Jeans project 4th floor slab rebar fabrication work.
  27. Mothers Heaven

    Mother's Heaven project 4th floor brick wall work & false ceiling, lintel casting work.

    Universal Jeans Ltd.

    Universal Jeans project 3rd floor column shutter fitting work.

    Diamond Heights

    Diamond Heights project pre-cast pile casting work.
  28. Mothers Heaven

    Mother's Heaven project 6th floor slab casting & 7th floor column, sw rebar fabrication, shuttering work.

    Universal Jeans Ltd.

    Universal Jeans project 2nd floor column shuttering work.

    Diamond Heights

    Diamond Heights project pre-cast pile casting work.

    National Hospital

    National Hospital project finishing work.
  29. Dr. Salim Ahmed

    Dr. Salim Ahmed project roof top slab & ribbes re-bar fabrication work

    Mothers Heaven

    Mother's Heaven project 6th floor roof beam rebar fabrication work

    Universal Jeans Ltd.

    Universal Jeans Ltd. project 1st floor roof beam & roof slab casting work.

    Diamond Heights

    Diamond Heights project bed making work & rcc precast pile rebar fabrication work

    National Hospital

    National Hospital floor casting & rcc work
  30. Bakul Monzil

    Bokul Monjil project 8th floor roof beam re-bar fabrication work

    Mothers Heaven

    Mothers Heaven Project 5th floor rebar fabrication work & 1st & 2nd floor brick wall work, plaster, chipping work

    Universal Jeans Ltd.

    Universal Jeans Ltd. project gr. floor roof slab casting work

    Dr. Salim Ahmed

    Dr. Salim Ahmed Project 3rd floor roof beam slab re-bar fabrication work

    Diamond Heights

    Diamond Heights project pre-cast pile drive work ongoing
  31. Mothers Heaven

    Mothers Heaven project 5th floor column, sw, rcc casting work.

    Universal Jeans Ltd.

    Universal Jeans Ltd project ground floor column casting work.

    Diamond Heights

    Diamond Heights project pre-cast pile drive work.

    Bakul Monzil

    Bokul Monjil Project 7th floor roof slab work complete.

    Dr. Salim Ahmed

    Dr. Salim Ahmed project 2nd floor roof beam slab casting work.

    National Hospital

    National Hospital project logo wall re-bar fabrication work.
  32. Mothers Heaven

    Mothers Heaven project 4th floor roof slab rebar fabrication work

    National Hospital

    National Hospital Dropping Zone area's rebar fabrication work

    Universal Jeans Ltd.

    Universal Jeans Ltd basement roof slab casting work

    Dr. Salim Ahmed

    Dr. Salim Ahmed 1st floor roof slab casting work
  33. Bakul Monzil

    Bokul monjil project 7th floor roof slab casting

    Mothers Heaven

    Mothers Heaven project 3rd floor roof slab casting

    Dr. Salim Ahmed

    Dr. Salim Ahmed project ground floor roof beam shutter work running
  34. Mothers Heaven

    Mother Heaven project 3rd floor column casting

    Bakul Monzil

    Bokul Monzil project 6th floor roof slab casting
  35. Bakul Monzil

    Bakul Monzil project 6th Floor Roof Slab RCC Casting Work

    Mothers Heaven

    Mother Heaven project 2nd Floor Roof Beam Slab Shuttering Work
  36. Mothers Heaven

    Mothers Heaven project 2nd Floor Column, Shear Wall, Lift Wall Rebar Fabrication Work
  37. Bakul Monzil

    Bakul Monzil project 6th Floor Column SW Stair Casting Work