Construction Camera

Bokul Monzil

  1. Bakul Monzil project 8th floor brick work and Meter room brick work.
  2. Bakul Monzil project 7th floor lintel, ceiling plaster and false slab shutter work and brick work.
  3. Bakul Monzil project 6th floor brick work, 7th floor brick work and OHWR coloum work.
  4. Bakul Monjil project 5th floor brick work and 6th floor ceiling plaster work.
  5. Bakul Monjil project 3rd floor plaster work, 4th floor brick wall work and 5th floor brick wall layout work.
  6. Bakul Monzil project 2nd floor electric groove cutting, grill fitting and toilet door fitting work and 3rd floor brick wall work.
  7. Bokul Monjil project 8th floor roof beam re-bar fabrication work
  8. Bokul Monjil Project 7th floor roof slab work complete.
  9. Bokul monjil 7th floor roof slab casting
  10. Bokul Monzil 6th floor roof slab casting
  11. 6th Floor Roof Slab RCC Casting Work
  12. 6th Floor Column SW Stair Casting Work