Construction Camera

Bakul Monzil

  1. Bakul Monjil project successfully completed and handover.
  2. Bakul Monzil project out side plaster and groove work completed.
  3. Bakul Monzil project boundary wall grill, lift machine room plaster work.
  4. Bakul Monzil project east, west out side plaster work.
  5. Bakul Monzil project void portion plaster work and roof top one room and OHWR second bottom slab rebar placing work.
  6. Bakul Monzil project 8th floor brick wall work, 9th floor inside plaster work, Roof top second lift column casting work.
  7. Bakul Monzil project 8th floor brick work and Meter room brick work.
  8. Bakul Monzil project 7th floor lintel, ceiling plaster and false slab shutter work and brick work.
  9. Bakul Monzil project 6th floor brick work, 7th floor brick work and OHWR coloum work.
  10. Bakul Monjil project 5th floor brick work and 6th floor ceiling plaster work.
  11. Bakul Monjil project 3rd floor plaster work, 4th floor brick wall work and 5th floor brick wall layout work.
  12. Bakul Monzil project 2nd floor electric groove cutting, grill fitting and toilet door fitting work and 3rd floor brick wall work.
  13. Bokul Monjil project 8th floor roof beam re-bar fabrication work
  14. Bokul Monjil Project 7th floor roof slab work complete.
  15. Bokul monjil project 7th floor roof slab casting
  16. Bokul Monzil project 6th floor roof slab casting
  17. Bakul Monzil project 6th Floor Roof Slab RCC Casting Work
  18. Bakul Monzil project 6th Floor Column SW Stair Casting Work